The following text was automatically extracted from the image on this page using optical character recognition software:
'35
CHROMA KEY SLIDE COMIN AIRPORT
TAKE CK SLIDE: AIRPORT Two construction companies today filed suit BLOXOM: LOWER LEFT
against Dallas-Fort Worth Airport seeking (M) $5- million-dollars in damages they claimed were sustained through improper work schedules and contract changes made by the airport board. The petitions were filed in federal court in Dallas by Guy James Construction Company and Howard Electric Company. The firms said they were forced to pay what they called "astronomical" labor and equipment rental costs last September.: The plaintiffs charged that the airport board became "obsessed" with having a gala opening ball that month and wanted the airport to look completed even when it wasn't~