Texas Construction and Maintenance Report: May 2001 Page: Page179
536 p. ; 28 cm.View a full description of this report.
Extracted Text
The following text was automatically extracted from the image on this page using optical character recognition software:
MIS.CIS.19
DISTRICT 11MONTHLY STATE LET CONSTRUCTION REPORT
AS OF MAY 09, 2001PAGE 179
************************************************************************************************************************************
* ' CONTRACT ' AMOUNT THIS 'TOTAL ESTIMATE ' % *
* CONTRACT IDENTIFICATION AND INFORMATION LENGTH AMOUNT ESTIMATE TO DATE COMP*
************************************************************************************************************************************
POLK US 59 (CORRIGAN) 16.307 4,984,345.20' 0.00' 0.00 0.0'
FM 942 FM 62 (CAMDEN)II.
1877-02-012
- CSR 1877-2-12 . REHAB EXISTING ROADWAY .
WORK ORDER- 00-00-00 WORK BEGAN- 00-00-00 - *************************************************I
DATE WORK COMPLETED- . TIME COMPUTED- 00-00-00 * NO CURRENT ESTIMATE PROCESSED AT THE *
CONTRACT WORKING DAYS- 205 -ADDL DAYS GRANTED- 0 * TIME OF THIS RUN *I
NORKING DAYS CHARGED- 0 PERCENT TIME USED-' 0 **************************************************I
KINSEL INDUSTRIES, INC.
CONTRACT 02013003 TOTALS 4,984,345.20! 0.00 0.00! 0.0!
***********************************************************************************************************************************4
RbLK CR 219 AT PINEY CREEK ' 0.053 ' 143,571.45 0.00 0.00' 0.0
CR
0911-04-031. IIII I
BR 2001(36)OX REPLACE BRIDGE AND APPROACHESWR D -10 OKEN3-
WORK ORDER- 03-19-01 WORK BEGAN-- 04-30-01 IIII I
DATE WORK COMPLETED- TIME COMPUTED- 04-04-01
CONTRACT WORKING DAYS- 60 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0
SMITH & CO.IIIII I
CONTRACT 02013031 !1 TOTALS 143,571.45! 0.00; 0.00 0.0
**************************************************************************************************************************
POLK AT MORGAN CREEK, 1.3 MI. N. OF FM 1988 ' 0.100 222,116.76 0.00' 0.00' 0.0'
US 59 .
0177-01-085IIIII I
MC 177-1-85 EROSION CONTROL
WORK ORDER- 03-06-01 WORK BEGAN- 00-00-00
DATE WORK COMPLETED- TIME COMPUTED- 03-22-01
CONTRACT WORKING DAYS- 40 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0
AJAX EQUIPMENT COMPANYIIIII I
CONTRACT 02013095 !1 TOTALS 222,116.76! 0.00 0.00 0.0
*************************************************************************** ****************************************************
POLK US 59 ' 13.507 2,558,687.49 35,204.37 2,047,689.86' 84.2'
FM 352 5.5 MILES EAST
0929-01-017
STP 2000(369)HES SAFETY TREAT FIXED OBJECTS, REMOVE
TREESIIIII I
WORK ORDER- 05-09-00 WORK BEGAN- 05-30-00IIII I
DATE WORK COMPLETED- TIME COMPUTED- 05-25-00
CONTRACT WORKING DAYS- 195 ADDL DAYS GRANTED- 4
WORKING DAYS CHARGED- 127 PERCENT TIME USED- 63
PINTO CONSTRUCTION CO. , INC.IIIII I
CONTRACT 04003048 TOTALS ! 2,558,687.49! 35,204.37! 2,047,689.86! 84.2!
********************************************************************************** ***********************************
POLK CR 247 AT BIG SANDY CREEK 0.070 157,750.00 0.00' 0.00 0.01
CR
0911-04-032
BR 2001(37)OX REPLACE BRIDGE AND APPROACHES
WORK ORDER- 05-09-01 WORK BEGAN- 00-00-00 I*************************************************I
DATE WORK COMPLETED- TIME COMPUTED- 05-25-01 * NO CURRENT ESTIMATE PROCESSED AT THE *51 I.
CONTRACT WORKING DAYS- 60 ADDL DAYS GRANTED- 0 * TIME OF THIS RUN *)
WORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 *************************************************I
DIAMOND K EQUIPMENT INC.II 'I I
CONTRACT 04013034 !1 TOTALS 157,750.00! 0.00! 0.00! 0.0
*************************************************************** ********* *********************************
POLK US 59 (N) 8.993 3,529,906.93 117,000.04 1,325,932.12' 39.5'
LP 116 US 59 (S)
0176-07-011
AR 176-7-11 REHAB EXISTING ROADWAYIIIII I
WORK ORDER- 07-10-00 WORK BEGAN- 07-25-00
DATE WORK COMPLETED- TIME COMPUTED- 07-26-00
CONTRACT WORKING DAYS- 160 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 109 PERCENT TIME USED- 68
SOUTH COAST CONSTRUCTION, INC.
CONTRACT 05003007 TOTALS 3,529,906.93! 117,000.04! 1,325,932.12! 39.5!
*************************************************************** ********************************************************
Upcoming Pages
Here’s what’s next.
Search Inside
This report can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Report.
Texas. Department of Transportation. Construction Division. Texas Construction and Maintenance Report: May 2001, report, May 1, 2001; Austin, Texas. (https://texashistory.unt.edu/ark:/67531/metapth1032004/m1/183/: accessed July 17, 2024), University of North Texas Libraries, The Portal to Texas History, https://texashistory.unt.edu; crediting UNT Libraries Government Documents Department.