Texas Construction and Maintenance Report: May 2001 Page: Page46
536 p. ; 28 cm.View a full description of this report.
Extracted Text
The following text was automatically extracted from the image on this page using optical character recognition software:
MIS.CIS. 19
DISTRICT 02MONTHLY LOCAL LET MAINTENANCE REPORT
AS OF MAY 09. 2001PAGE 46
*************************************************************** I **********I************ ** ******** ******** ***
* CONTRACT AMOUNT THIS TOTAL ESTIMATE % *
* CONTRACT IDENTIFICATION AND INFORMATION LENGTH I AMOUNT ESTIMATE TO DATE COMP*
**********************************************************************************************************************************
JACK US 281 NB & SB 0.010 20,553.65 0.00+8,811.6550.8
US0281 US380 IN JACK COUNTY
6062-92-001
SUP - 606292001 PICNIC AREA MAINTENANCE
NORK ORDER- 10-01-00 NORK BEGAN- 10-02-00 I *********************************************I
DATE NORK COMPLETED- TIME COMPUTED- 10-02-00 * NO CURRENT ESTIMATE PROCESSED AT THE *
CONTRACT WORKING DAYS- 365 ADDL DAYS GRANTED- 0 * TIME OF THIS RUN *1
NORKING DAYS CHARGED- 211 PERCENT TIME USED- 57 ********************************I****************
TIBH INDUSTRIES, INC. NAUECUTY D
MONT AGUE COUNTY , IDCIIIII I
CONTRACT 09000201 TOTALS 20,553.65! 0.00; 8,811.65 50.8!
*********************************************************************************************************************************
JACK VARIOUS LOCATIONS IN 347.630 ' 166,704.00'0.0010.00 0.0
US0281 JACK COUNTY
6059-99-001
RMC - 605999001 MORNING HIGHWAY RIGHT-OF-NAY JACK(
CO.IIIII
I I
NORK ORDER- 06-01-01 ORK BEGAN- 00-00-00 I************************************************I
DATE NORK COMPLETED- TIME COMPUTED- 06-07-01 * NO CURRENT ESTIMATE PROCESSED AT THE *I
CONTRACT WORKING DAYS- 127 ADDL DAYS GRANTED- 0 * TIME OF THIS RUN *I
NORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 ************************************************
R AND R MONINGIIII
CONTRACT 11000203 I1 TOTALS 166,704.00! 0.00! 0.00 0.0
************************************************************************************************************************************
JACK VARIOUS LOCATIONS IN ' 347.630 ' 183,745.74' 0.00' 137,650.22' 74.9'
US0281 JACK COUNTY 037-69-001
6037-69-001
RMC - 603769001 HONING HIGHWAY RIGHT-OF-NAYIIIII I
NORK ORDER- 07-08-99 NORK BEGAN- 07-12-99 *************************************************
DATE NORK COMPLETED- TIME COMPUTED- 07-19-99 * NO CURRENT ESTIMATE PROCESSED AT THE * I
CONTRACT WORKING DAYS- 129 ADDL DAYS GRANTED- 0 * TIME OF THIS RUN *I
NORKING DAYS CHARGED- 43 PERCENT TIME USED- 33 ************************************************I
R AND R MONINGIIIII I
CONTRACT 12980203 TOTALS 183,745.74! 0.00! 137,650.22! 74.9!
******************************************************************************************* **************************************
JOHNSON VARIOUS LOCATIONS IN 101.900 228,012.85' 0.00' 0.00' 0.0'
SH0174 JOHNSON COUNTY 066-83-001
6066-83-001IIII I
RMC - 606683001 THERMO STRIPINGIIIII
NORK ORDER- 05-03-01 NORK BEGAN- 00-00-00 I**************** **************** I
DATE WORK COMPLETED- TIME COMPUTED- 05-10-01 I* NO CURRENT ESTIMATE PROCESSED AT THE * I
CONTRACT WORKING DAYS- 43 ADDL DAYS GRANTED- 0 I* TIME OF THIS RUN *I
NORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 **************************************************I
UNITED EQUIPMENT RENTALS GULF, L.P.
CONTRACT 03010202 TOTALS 228,012.85! 0.00! 0.00 0.0!
************************************************************************************************************************************
JOHNSON VARIOUS LOCATIONS IN 362.000 ' 167,272.50' 0.0010.00 0.0'
US0067 JOHNSON COUNTY
6068-06-001
RMC - 606806001 GUARDRAIL REPAIR!
NORK ORDER- 00-00-00 NORK BEGAN- 00-00-00 *** * *********************************
DATE NORK COMPLETED- TIME COMPUTED- 00-00-00 I * NO CURRENT ESTIMATE PROCESSED AT THE * I
CONTRACT WORKING DAYS- 718 ADDL DAYS GRANTED- 0 * TIME OF THIS RUN *I
NORKING DAYS CHARGED- 0 PERCENT TIME USED- 0 *************************************************I
JOHN COPELAND ENTERPRISES, INC. I
CONTRACT 04010204 !1 TOTALS 167,272.50! 0.00 0.00! 0.0!
***********************************************************************************************************************************K
JOHNSON IH35H 32 TO 33 / 3.0 MI S. OF BURLESON ' 0.010 ' 93,770.42 11,393.20 68,984.02' 73.5'
IH0035H IH35N 31 TO 32 / 5.8 MI S. OF BURLESON
6060-08-001
SUP - 606008001 REST ARA MAINTENANCE
NORK ORDER- 07-01-00 NORK BEGAN- 07-01-00
DA TE NORK COMPL ET ED- TIME COMPUT ED- 07-01-00IIII I
CONTRACT WORKING DAYS- 365 ADDL DAYS GRANTED- 0WN S G0TI E
NORKING DAYS CHARGED- 304 PERCENT TIME USED- 83III I
TIBH INDUSTRIES, INC. I
MONTAGUE COUNTY, IDC
CONTRACT 06000207 TOTALS 93,770.42! 11,393.20! 68,984.02! 73.5!
*********************************************************************************************************************it
Upcoming Pages
Here’s what’s next.
Search Inside
This report can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Report.
Texas. Department of Transportation. Construction Division. Texas Construction and Maintenance Report: May 2001, report, May 1, 2001; Austin, Texas. (https://texashistory.unt.edu/ark:/67531/metapth1032004/m1/50/: accessed July 17, 2024), University of North Texas Libraries, The Portal to Texas History, https://texashistory.unt.edu; crediting UNT Libraries Government Documents Department.