MIS.CIS.19
DISTRICT 24MONTHLY STATE LET MAINTENANCE REPORT
AS OF MAY 09, 2001PAGE 509
********************************************************************************************************************************
* ' CONTRACT AMOUNT THIS TOTAL ESTIMATE % *
* CONTRACT IDENTIFICATION AND INFORMATION LENGTH AMOUNT ESTIMATE TO DATE COMP*
*********************************************************************************************************************************
CULBERSON REFERENCE MARKER 116+0.0 ' 28.962 467,927.68 0.00 344,880.26' 58.7'
US0062 REFERENCE MARKER 136+1..5
6029-37-001
RMC - 602937001 REMOVE AND INSTALL NEN GUARD FENCE
WORK ORDER- 11-16-98 NORK BEGAN- 11-16-98 ******************K****************************** -
DATE NORK COMPLETED- TIME COMPUTED- 11-16-98 * NO CURRENT ESTIMATE PROCESSED AT THE * I
CONTRACT WORKING DAYS- 60 ADDL DAYS GRANTED- 0 * TIME OF THIS RUN *1
NORKING DAYS CHARGED- 99 PERCENT TIME USED- 165 I************************************************** I
S TE INC.IIIII
CONTRACT 06984003 TOTALS 467,927.68 0.00 344,880.26 58.7!
*************************************************************** ********* *******************K************************************* *
EL PASO IH-10 (LP 375/TRANS MOUNTAIN) 560.000 1,853,406.25; 0.00' 415,411.50' 22.4'
IH0010 IH-10 (FM 793/FABENS)
6057-54-001
RMC - 605754001 SLEEPING ON VARIOUS
NORK ORDER- 10-01-00 NORK BEGAN- 10-01-00 ******************K******************************
DATE NORK COMPLETED- TIME COMPUTED- 10-01-00 * NO CURRENT ESTIMATE PROCESSED AT THE *I
CONTRACT WORKING DAYS- 730 ADDL DAYS GRANTED- 0 1* TIME OF THIS RUN *1
WORKING DAYS CHARGED- 182 PERCENT TIME USED- 24 **************************************************
INFRASTRUCTURE SERVICES, INC.
CONTRACT 07004003 1 TOTALS 1,853,406.25! 0.00! 415,411.50! 22.4!
*********************************************************************************************************************************DISTRICT CONTRACT AMOUNT
DISTRICT ESTIMATES THIS MONTH
DISTRICT TOTAL ESTIMATES PAID TO DATE2,321,333.93
0.00
760,291.76
Upcoming Pages
Here’s what’s next.
Search Inside
This report can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Report.
Texas. Department of Transportation. Construction Division. Texas Construction and Maintenance Report: May 2001, report, May 1, 2001; Austin, Texas. (https://texashistory.unt.edu/ark:/67531/metapth1032004/m1/513/: accessed July 17, 2024), University of North Texas Libraries, The Portal to Texas History, https://texashistory.unt.edu; crediting UNT Libraries Government Documents Department.