MIS.CIS. 19
DISTRICT 01MONTHLY STATE LET CONSTRUCTION REPORT
AS OF MAY 09, 2001PAGE 3
***********************************************************************************************************************************
* ' CONTRACT ' AMOUNT THIS 'TOTAL ESTIMATE % *
* CONTRACT IDENTIFICATION AND INFORMATION LENGTH AMOUNT ESTIMATE TO DATE COMP*.
***********************************************************************************************************************************4
GRAYSON SH 56 0.024 ' 446,263.84' 0.0' 410,867.00' 96.9'
SH 56 @ POST OAK CREEK IN SHERMAN
0045-03-030
BR 2000(484) REPLACEMENT OF AN EXISTING BRIDGE
FAC
NORK ORDER- 08-07-00 NORK BEGAN- 08-27-00
DATE NORK COMPLETED- TIME COMPUTED- 08-23-00
CONTRACT NORKING DAYS- 98 ADDL DAYS GRANTED- 3II I
NORKING DAYS CHARGED- 101 PERCENT TIME USED- 100HNYI I
HODGES AND SON CONSTRUCTION COMPANY, INC.IIIII I
CONTRACT 07003111 TOTALS 446,263.84! 0.00! 410,867.00! 96.9!
K********************************************************************************************************** **********************
GRAYSON N OF US 69 2.937 ' 7,538,790.90' 129,549.54 '5,229,164.96'73.0
US 82 FANNIN C/L
0045-19-015
tC 45-19-15 GR, STRS, BASE & SURF
NORK ORDER- 09-03-98 NORK BEGAN- 09-23-98
*DATE NORK COMPLETED- TIME COMPUTED- 09-19-98
CONTRACT WORKING DAYS- 274 ADDL DAYS GRANTED- 57
WORKING DAYS CHARGED- 166 PERCENT TIME USED- 50
R'dSHING PAVING COMPANYIIIII I
CONTRACT 07983003 ! TOTALS 7,538,790.90 129,549.54 5,229,164.96 73.0!
****************************************************************K*************************** *********************************** S
GRAYSON FM 1417 8.550' 12,929,461.49 45,212.78 76,962.73 0.6'
US 82 0.4 MILES NEST OF US 69
0045-19-026IIII I
NH 2000(494) NEN LOCATION OF US 82; GR STRS &
PAY
NORK ORDER- 10-05-00 NORK BEGAN- 01-15-01IIII I
DATE NORK COMPLETED- TIME COMPUTED- 01-15-01 t
CONTRACT WORKING DAYS- 450 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 28 PERCENT TIME USED- 6
RUSHING PAVING COMPANYIIIII I
CONTRACT 08003004 TOTALS 12,929,461.49! 45,212.78! 76,962.73! 0.6!
******************************************************************************************** *********************************** S
GRAYSON CR 501 @ EAST PRONG WHITES CREEK 0.227 ' 492,359.97 61,820.64 411,802.89 87.1
CR
0901-19-102 t
BR 99(499)OX REPLACEMENT OF AN EXISTING BRIDGE
FAC
MORK ORDER- 09-21-00 WORK BEGAN- 10-16-00
DATE NORK COMPLETED- TIME COMPUTED- 10-07-00 I
CONTRACT WORKING DAYS- 60 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 53 PERCENT TIME USED- 88
BONIE BRIDGE, LTD.II II I
CONTRACT 08003155 TOTALS 492,359.97! 61,820.64 411,802.89! 87.1!
*******************************************************************************************************************************
GRAYSON AT SAND CREEK 0.928 ' 1,500,223.13 12,084.80 1,330,581.58 93.4
SH 56
i 0045-03-023
B R 9 9 ( 1 3 ) R E P L A C E B R I D G E A N D A P P R O A C H ESWR D -2 9 O K E N0 9
MORK ORDER- 09-24-99 NORK BEGAN- 11-04-99IIII I
DATE WORK COMPLETED- TIME COMPUTED- 10-10-99
CONTRACT WORKING DAYS- 180 ADDL DAYS GRANTED- 14
WORKING DAYS CHARGED- 195 PERCENT TIME USED- 100II I I
RUSHING PAVING COMPANYIIIII I
CONTRACT 08993030 TOTALS 1,500,223.13! 12,084.80! 1,330,581.58! 93.4!
*************************************************************************************************************************************
GRAYSON 1.625 KM N OF ELM STREET 8.803 3,326,762.86' 12,239.80' 3,129,294.91 99.0'
SH 289 FM 902
0091-01-029
STP 99(433)RM GR, LIME TR SUB, BS, STRS & SURF
WORK ORDER- 09-16-99 NORK BEGAN- 09-23-99
DATE NORK COMPLETED- TIME COMPUTED- 10-02-99
CONTRACT WORKING DAYS- 300 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 191 PERCENT TIME USED- 63
D. L. LENNON INCORPORATED - CONTRACTORIIIII I
CONTRACT 08993086 ! TOTALS 3,326,762.86! 12,239.80 3,129,294.91 99.0!
**************************************************************4*************************************************************K*****
Upcoming Pages
Here’s what’s next.
Search Inside
This report can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Report.
Texas. Department of Transportation. Construction Division. Texas Construction and Maintenance Report: May 2001, report, May 1, 2001; Austin, Texas. (https://texashistory.unt.edu/ark:/67531/metapth1032004/m1/7/: accessed July 17, 2024), University of North Texas Libraries, The Portal to Texas History, https://texashistory.unt.edu; crediting UNT Libraries Government Documents Department.