MIS.CIS.19 MONTHLY STATE LET CONSTRUCTION REPORT
DISTRICT 02 AS OF APR 08, 1999 PAGE 28
* * * CONTRACT * AMOUNT THIS * TOTAL ESTIMATE * % *
* CONTRACT IDENTIFICATION AND INFORMATION * LENGTH * AMOUNT * ESTIMATE * TO DATE * COMP*
TARRANT AT HARMOOD ROAD ' .001 ' 124,865.40' 10,081.80' 125,393.76' 99.9'
SH 360 IN GRAND PRAIRIE'' '
2266-02-100 ''
C 2266-2-100 TRAFFIC SIGNALS''''
NORK ORDER- 08-21-98 NORK BEGAN- 11-24-98 ''''
DATE NORK COMPLETED- TIME COMPUTED- 11-19-98 '' ''
CONTRACT WORKING DAYS- 45 ADDL DAYS GRANTED- 5 ''''
NORKING DAYS CHARGED- 51 PERCENT TIME USED- 102 ''''
SHARROCK ELECTRIC, INC.' ''
CONTRACT 07983016 ' TOTALS ' 124,865.40' 10,081.80' 125,393.76' 99.9'
TARRANT GLENVIEN DR AT BOOTH CALLONAY IN ' .251 ' 589,650.93' 17,833.77' 156,489.92' 27.9'
CS RICHLAND HILLS''''
0902-48-187 '''
CM 94(18) INTERSECTION IMPROVEMENT''''
NORK ORDER- 10-01-98 NORK BEGAN- 02-08-99 '''
DATE NORK COMPLETED- TIME COMPUTED- 12-30-98 ''''
CONTRACT WORKING DAYS- 75 ADDL DAYS GRANTED- 0 ''- ''
WORKING DAYS CHARGED- 32 PERCENT TIME USED- 43 ''''
ARCHITECTURAL UTILITIES, INC.''''
CONTRACT 07983035 ' TOTALS ' 589,650.93' 17,833.77' 156,489.92' 27.9'
TARRANT 2.6 MI E OF IH 820 ' 2.997 ' 14,550,978.85' 427,545.08' 4,276,648.04' 30.9'
5P 303 FIELDER RD''''
2208-01-033 '''
STP 98(336)MM GR, STRS, SURF''''
NORK ORDER- 09-09-98 NORK BEGAN- 10-05-98 ' ''
DATE NORK COMPLETED- TIME COMPUTED- 09-25-98 ''''
CONTRACT NORKING DAYS- 491 ADDL DAYS GRANTED- 0 ''''
WORKING DAYS CHARGED- 128 PERCENT TIME USED- 26 ''''
AUSTIN BRIDGE & ROAD, INC.'''
CONTRACT 07983065 ' TOTALS ' 14,550,978.85' 427,545.08' 4,276,648.04' 30.9'
TARRANT VARIOUS LOCATIONS ' .001 ' 111,630.52' 2,899.43' 94,714.92'100.0'
VA'''
0902-00-057 ''
CPM 902-00-57 SIGN REPLACEMENT'' '
NORK ORDER- 08-21-98 NORK BEGAN- 12-30-98 ''''
DATE NORK COMPLETED- 03-25-99 TIME COMPUTED- 11-19-98 ''''
CONTRACT NORKING DAYS- 90 ADDL DAYS GRANTED- 0 ''''
WORKING DAYS CHARGED- 64 PERCENT TIME USED- 71 ''''
0'HENRY SIGNS' ''
CONTRACT 07983078 ' TOTALS ' 111,630.52' 2,899.43' 94,714.92'100.0'
TARRANT ABRAM ST FROM BRONNING DR TO STADIUM DR ' .439 ' 1,842,202.02' 75,150.99' 1,686,337.06' 96.3'
NH INMARLINGTON''''
0902-48-265''''
CM 95(81) INTERSECTION IMPROVEMENTS''''
NORK ORDER- 10-16-97 NORK BEGAN- 06-22-98 '''
DATE NORK COMPLETED- TIME COMPUTED- 11-01-97 ''''
CONTRACT NORKING DAYS- 190 ADDL DAYS GRANTED- 0 ''''
WORKING DAYS CHARGED- 169 PERCENT TIME USED- 89 ''''
SITE CONCRETE, INC.
CONTRACT 08973026 ' TOTALS ' 1,842,202.02' 75,150.99' 1,686,337.06' 96.3'
TARRANT SH 183 (ON NESTPARK NAY) ' 2.025 ' 3,676,554.45' 25,570.02' 3,397,728.09' 98.3'
CS 0.1 MI S OF SH 10 IN EULESS''''
0902-48-191''''
STP 94(86)MM NIDEN RDNY''''
NORK ORDER- 10-16-97 NORK BEGAN- 11-19-97 ''''
DATE NORK COMPLETED- TIME COMPUTED- 11-01-97 ' ''
CONTRACT NORKING DAYS- 255 ADDL DAYS GRANTED- 66 ''''
WORKING DAYS CHARGED- 351 PERCENT TIME USED- 109 ''' '
SITE CONCRETE, INC.'' ''
CONTRACT 08973080 ' TOTALS ' 3,676,554.45' 25,570.02' 3,397,728.09' 98.3'4
0
Upcoming Pages
Here’s what’s next.
Search Inside
This report can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Report.
Texas. Department of Transportation. Construction Division. Texas Construction and Maintenance Report: April 1999, report, April 1, 1999; Austin, Texas. (https://texashistory.unt.edu/ark:/67531/metapth1033507/m1/32/: accessed July 17, 2024), University of North Texas Libraries, The Portal to Texas History, https://texashistory.unt.edu; crediting UNT Libraries Government Documents Department.