DISTRICT 12 AS OF JUL 10, 2000 PAGE 209
* * * CONTRACT * AMOUNT THIS * TOTAL ESTIMATE * % *
* CONTRACT IDENTIFICATION AND INFORMATION * LENGTH * AMOUNT * ESTIMATE * TO DATE * COMP*
************************************************************************************************************************************
HARRIS HUFFMEISTER RD ' 3.337 ' 17,201,563.91' 992,544.99' 11,689,840.48' 71.5'
FM 529 BARKER-CYPRESS
1006-01-048
STP 99(6)MM GR, STRS, BS CONC PVT
HARRIS HUFFMEISTER ROAD ' 4.510 ' 236,868.20 .00' 10,383.50' 4.6'
FM 529 BARKER-CYPRESS ROAD
, 1006-01-049
CM 99(7) INST ATMS
WORK ORDER- 12-29-98 WORK BEGAN- 02-22-99
DATE WORK COMPLETED- TIME COMPUTED- 01-14-99
CONTRACT WORKING DAYS- 408 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 304 PERCENT TIME USED- 75
* PATE & PATE ENTERPRISES, INC.
CONTRACT 11983046 ' TOTALS ' 17,438,432.11' 992,544.99' 11,700,223.98' 70.6'
************************************************************************************************************************************
HARRIS AT BW 8 N ' 1.474 ' 9,188,453.79' 359,257.81' 1,498,514.31' 16.9'
US 59
0177-07-101 ' ! } '
CM 2000(41) CONSTRUCT DIRECT CONNECTOR
HARRIS 0.8 MI N OF US 59(N) ' 2.732 ' 26,260,525.71' 611,286.87' 10,141,458.67' 40.2'
BW 8 0.3 MI E OF OLD HUMBLE RD (PHASE 1)
3256-02-053
STP 2000(40)MM CONST 4 MAIN LANES AND BRIDGE
WORK ORDER- 11-30-99 WORK BEGAN- 12-01-99
DATE MORK COMPLETED- TIME COMPUTED- 12-16-99
CONTRACT WORKING DAYS- 746 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 151 PERCENT TIME USED- 20
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
CONTRACT 11993001 ' TOTALS ' 35,448,979.50' 970,544.68' 11,639,972.98' 34.2'
************************************************************************************************************************************
HARRIS TMC/GREENWAY PLAZA/GALLERIA(W.SEG-PHA.1)' 29.960 ' 635,063.25' 70,240.41' 602,948.32' 98.8'
VA
0912-71-649
STP 94(341)TE TRANSPORTATION ENHANCEMENT
WORK ORDER- 01-03-00 WORK BEGAN- 02-21-00
DATE WORK COMPLETED- TIME COMPUTED- 01-19-00
CONTRACT WORKING DAYS- 120 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 80 PERCENT TIME USED- 67
JERDON ENTERPRISE, INC.
CONTRACT 11993025 ' TOTALS ' 635,063.25' 70,240.41' 602,948.32' 98.8'
************************************************************************************************************************************
HARRIS 1488 M NEST OF MASON ROAD ' 2.861 ' 7,845,176.41' 619,380.76' 2,990,705.78' 39.7'
US 290 1394 M EAST OF MASON ROAD
0050-06-055
CM 2000(38) GR, STRS, BS, DRAIN, CONC PAV, ACP
ETC.
WORK ORDER- 01-18-00 WORK BEGAN- 02-18-00
DATE WORK COMPLETED- TIME COMPUTED- 02-03-00
*CONTRACT WORKING DAYS- 225 ADDL DAYS GRANTED- 3
WORKING DAYS CHARGED- 68 PERCENT TIME USED- 30
1 I 1
KINSEL INDUSTRIES, INC.
CONTRACT 11993048 ' TOTALS ' 7,845,176.41' 619,380.76' 2,990,705.78' 39.7'
************************************************************************************************************************************
HARRIS BETWEEN TIDWELL/HAMMERLY & IH 610 N LP ' 41.270 ' 1,283,705.12' 34,782.00' 458,755.94' 37.2'
VA BETWEEN BW 8 AND GREENS BAYOU
'912-71-501
CM 96(728) CONST BIKE ROUTES,LANES & BIKE/PED
TRAIL
WORK ORDER- 01-21-00 WORK BEGAN- 03-28-00
DATE WORK COMPLETED- TIME COMPUTED- 02-06-00
CONTRACT WORKING DAYS- 123 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 67 PERCENT TIME USED- 54
INFRASTRUCTURE SERVICES, INC.
CONTRACT 11993063 ' TOTALS ' 1,283,705.12' 34,782.00' 458,755.94' 37.2'
************************************************************************************************************************************MIS. CIS. 19
MONTHLY STATE LET CONSTRUCTION REPORT
Upcoming Pages
Here’s what’s next.
Search Inside
This report can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Report.
Texas. Department of Transportation. Construction Division. Texas Construction and Maintenance Report: July 2000, report, July 1, 2000; Austin, Texas. (https://texashistory.unt.edu/ark:/67531/metapth1115086/m1/217/: accessed July 17, 2024), University of North Texas Libraries, The Portal to Texas History, https://texashistory.unt.edu; crediting UNT Libraries Government Documents Department.