MIS.CIS.19 ' MONTHLY STATE LET CONSTRUCTION REPORT
DISTRICT 15. AS OF JUL 10, 2000 PAGE 284
* * * CONTRACT * AMOUNT THIS * TOTAL ESTIMATE * % *
* CONTRACT IDENTIFICATION AND INFORMATION * LENGTH * AMOUNT * ESTIMATE * TO DATE * COMP*
************************************************************************************************************************************
ATASCOSA 2.51 KM SO OF SP 199 ' 15.041 ' 3,766,226.26' .00' 3,875,001.32' 99.9'
IH 37 1.29 KM N OF US 281A (N OF CAMPBELLTON)
0073-05-058 ' 1 }
IM 37-2(66) SEAL COAT & ACP
WORK ORDER- . 07-13-99 NORK BEGAN- 07-29-99 ' '**************************************************
DATE NORK COMPLETED- TIME COMPUTED- 07-29-99 ' '* NO CURRENT ESTIMATE PROCESSED AT THE *
CONTRACT WORKING DAYS- 108 ADDL DAYS.GRANTED- 0 ' '* TIME OF THIS RUN *
NORKING DAYS CHARGED- 91 PERCENT TIME USED- 84 '**************************************************
DEAN NORD COMPANY, LTD. ' ' ' 1
CONTRACT 04993062 ' TOTALS ' 3,766,226.26' .00' 3,875,001.32' 99.9'
ATASCOSA BEXAR C/L, S ' 7.205 ' 16,236,475.65' 886,896.35' 7,288,665.94' 47.2'
IH 37 1.70MI N OF SH 97
0073-10-037
IM 37-7(42) REHAB EXISTING ROADAY ' ' '
WORK ORDER- 10-14-99 NORK BEGAN- 10-20-99 '''.
DATE NORK COMPLETED- TIME COMPUTED- 10-30-99
CONTRACT WORKING DAYS- 547 ADDL DAYS GRANTED- 6
WORKING DAYS CHARGED- 122 PERCENT TIME USED- 22
HUNTER INDUSTRIES, INC.
CONTRACT 07993059 ' TOTALS ' 16,236,475.65' 886,896.35' 7,288,665.94' 47.2'
************************************************************************************************************************************
ATASCOSA 0.04 MI N OF FM 1470, S ' 5.620 ' 1,011,632.19' 158.61' 1,327,828.79' 99.9'
US5281 ' 1.80 MI S OF FM 3006
0073-03-054 ' ' '1'
STP 99(453)RM BASE, SEAL COAT, ACP ' ' '
NORK ORDER- 10-21-99 NORK BEGAN- 11-18-99
DATE WORK COMPLETED- TIME COMPUTED- 11-06-99
CONTRACT WORKING DAYS- 43 ADDL DAYS GRANTED- 37 ' ' 'I'
WORKING DAYS CHARGED- 49 PERCENT TIME USED- 61
HUNTER INDUSTRIES, INC. } ' ','
CONTRACT 09993010 ' TOTALS ' 1,011,632.19' 158.61' 1,327,828.79' 99.9'
************************************************************************************************************************************
BANDERA AT PIPE CREEK, 0.31 MI E OF FM 1283 ' .587 ' 1,190,458.92' 207,083.02' 488,030.64' 43.1'
SH 16.' ' ' '
0291-07-025
ER 2000(254) GRAD, STR, BASE, SURF
NORK ORDER- 03-27-00 NORK BEGAN- 04-10-00
DATE NORK COMPLETED- TIME COMPUTED- 04-12-00
CONTRACT WORKING DAYS- 105 ADDL DAYS GRANTED- 0 '
WORKING DAYS CHARGED- 44 PERCENT TIME USED- 42 '1
E. E. HOOD &SONS, INC.''
. CONTRACT 02003094 ' TOTALS ' 1,190,458.92' 207,083.02' 488,030.64' 43.1'
BANDERA PR 37 ' 5.150 ' 2,092,738.14' 92,545.18' 760,756.52' 38.2'
FM 1283 MEDINA C/L ' ' ' '
1730-01-028 ' ' ' "
AR 1730-1-28 GRAD, STR, BASE, SURF
WORK ORDER- 01-03-00 NORK BEGAN- 02-07-00
DATE WORK COMPLETED- TIME COMPUTED- 01-19-00
CONTRACT WORKING DAYS- 170 ADDL DAYS GRANTED- 0
WORKING DAYS. CHARGED- 80 PERCENT TIME USED- 47
CAPITAL EXCAVATION COMPANY
CONTRACT 10993065 ' TOTALS ' 2,092,738.14' 92,545.18' 760,756.52' 38.2'
************************************************************************************************************************************
BEXAR DISTRICTIDE ON INTERSTATE HIGHAYS ' .001 ' 1,305,840.00' 110,852.02' 457,987.87' 36.5'
VA. ' '
0915-00-060
IM 37-2(69) REPLACE GUARD RAIL TERMINAL ANCHOR
SECTS -
1I1I11 I
NORK ORDER- 02-15-00 WORK BEGAN- 03-14-00 '1
DATE WORK COMPLETED- TIME-COMPUTED- 03-02-00
CONTRACT WORKING DAYS- 180 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 59 PERCENT TIME USED- 33
INFRASTRUCTURE SERVICES, INC. '
CONTRACT 01003008 ' TOTALS ' 1,305,840.00' 110,852.02' 457,987.87' 36.5'
************************************************************************************************************************************-f
Upcoming Pages
Here’s what’s next.
Search Inside
This report can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Report.
Texas. Department of Transportation. Construction Division. Texas Construction and Maintenance Report: July 2000, report, July 1, 2000; Austin, Texas. (https://texashistory.unt.edu/ark:/67531/metapth1115086/m1/292/: accessed July 17, 2024), University of North Texas Libraries, The Portal to Texas History, https://texashistory.unt.edu; crediting UNT Libraries Government Documents Department.