APRIL 2011
Table 6-3. Cost Comparison for Chlorine Sources'
Capital Cost O & M Cost
Chlorine Total3
Source Civil;Electrical Chlorine TT
etc. Equipment Total Annual Total
Commercial
Grade $103,000 $28;000 $221,000 $18,000 $203,000 $424,000
Hypochlorite -
On-Site
Hypochlorite $55,000 $85,000 $235,000 $14,000 $164;000 $399,000
Generation s
Gas Chlorine $103,000 $1,135,000 $2,080,000 $14;000 $159,000 $2,238,000
Notes:
1. Based on 10-mgd plant capacity and 100-lb of dry chlorine weight per day
2. Adding 40% for construction contingency and 20%.for.engineering
3. Total cost (present value) equals to total capital cost (present value)'+ total O & M cost (present value)
4. Commercial grade at 12.5%
5. 100-lb system at 0.8%
Table 6-4. Cost Comparison for Chlorine and UV Systems'
Capital Cost 0 & M Cost
Chlorine Tota
Source
Civil, Electrical Chlorine' Total Annual Total
etc. Equipment
On-Site
Hypochlorite $55,000 $85,000 $235,000 " $14,000 $164,000 $399,000
Generation 4
UV + Chlorine $33,000 $340,000 ' $627,000 $12,000 $139,000 $766,000
feed ________ ______ _____
Notes:
1. Based on 10-mgd plant capacity for both systems and 100-lb of dry chlorine weight per day, and-dry chlorine
weight for chlorine feed system and UV system respectively.
2. Adding 40% for construction contingency and 20% for engineering
3. Total cost (present value) equals to total capital cost (present 'value) + total 'O & M cost (present value)
4. 100-lb system at 0.8%REGIONAL WATER SUPPLY FACILITIES PLAN
6-21
Upcoming Pages
Here’s what’s next.
Search Inside
This report can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Report.
Civil Systems Engineering, Inc. Addendum to Regional Water Supply Facilities Plan Final Report (April 2011), report, May 2011; Houston, Texas. (https://texashistory.unt.edu/ark:/67531/metapth839161/m1/173/: accessed July 16, 2024), University of North Texas Libraries, The Portal to Texas History, https://texashistory.unt.edu; crediting UNT Libraries Government Documents Department.