MONTHLY STATE LET CONSTRUCTION REPORT
AS OF MAY 09, 2001PAGE 468
******************************************************* **************** ************** ************************
* CONTRACT ' AMOUNT THIS TOTAL ESTIMATE % *
* CONTRACT IDENTIFICATION AND INFORMATION LENGTH AMOUNT ESTIMATE T TO DATE COMP*
************************************************************************************************************
JIM HOGG SH 285 19.985 ' 6,083,845.80' 0.00 0.00' 0.0'
FM 1017 SOUTH 20MILESI(
1227-01-021
STP 2001(101)R RECONSTRUCT AND ADD SHOULDERS -
NORK ORDER- 02-26-01 WORK BEGAN-' 00-00-00 II
DATE WORK COMPLETED- TIME COMPUTED- 03-14-01 III I
CONTRACT WORKING DAYS- 260 ADDL DAYS GRANTED- 0
WORKING DAYS CHARGED- 30 PERCENT TIME USED- 11
FOREMOST PAVING, INC. ~
CONTRACT 12003048 TOTALS 6,083,845.80, 0.001 0.00 0.0!
******************************************************************************************************************************* S
KENEDY AT US 77 0.001 2,308,000.00' 0.00' 1,036,513.11' 57.9'
US 77 4 MILES SOUTH OF SARITA
0327-02-043IIIII I
STP 2000(360)TE RECONSTRUCT SAFETY REST AREA
WORK ORDER- 07-25-00 NORK BEGAN- 09-11-00 ************************************************ I
DATE WORK COMPLETED- TIME COMPUTED- 08-10-00 * NO CURRENT ESTIMATE PROCESSED AT THE * I
CONTRACT WORKING DAYS- 200 ADDL DAYS GRANTED- 10 * TIME OF THIS RUN * I
NORKING DAYS CHARGED- 148 PERCENT TIME USED- 70 *************************************************I
RIO VALLEY CONSTRUCTION, INC.
CONTRACT 06003105 TOTALS 2,308,000.00! 0.00! 1,036,513.11! 57.9!
************************************************************************************************************************************
STARR US 83 THROUGH GARCIASVILLE 4.100 ' 3,325,500.78' 161,544.82 3,008,681.64' 94.2'
FM 1430 US 83
0039-13-014
STP 99(672)R WIDEN TO 52' F-FIIIII I
WORK ORDER- 12-16-99 W ORK BEGAN- 02-21-00IIDO-TE0
DA TE WORK COMPL E TED- T IME COMPUT ED- 01-01-00IIII I
CONTRACT WORKING DAYS- 198 ADDL DAYS GRANTED- 80
WORKING DAYS CHARGED- 257 PERCENT TIME USED- 92 I
FOREMOST PAVING, INC.
CONTRACT 09993006 ! TOTALS ! 3,325,500.78! 161,544.82! 3,008,681.64! 94.2!
****************************************************************************DISTRICT CONTRACT AMOUNT
DISTRICT ESTIMATES THIS MONTH
DISTRICT TOTAL ESTIMATES PAID TO345,094,589.76
17,276,409.53
112,345,675.15DATE
MIS.CIS.19
DISTRICT 21
Upcoming Pages
Here’s what’s next.
Search Inside
This report can be searched. Note: Results may vary based on the legibility of text within the document.
Tools / Downloads
Get a copy of this page or view the extracted text.
Citing and Sharing
Basic information for referencing this web page. We also provide extended guidance on usage rights, references, copying or embedding.
Reference the current page of this Report.
Texas. Department of Transportation. Construction Division. Texas Construction and Maintenance Report: May 2001, report, May 1, 2001; Austin, Texas. (https://texashistory.unt.edu/ark:/67531/metapth1032004/m1/472/?rotate=180: accessed July 17, 2024), University of North Texas Libraries, The Portal to Texas History, https://texashistory.unt.edu; crediting UNT Libraries Government Documents Department.